Monday, November 10, 2008

Wille's sleepover

Wille will be heading out next Monday (the 17th) with a load of supplies. He's going to work on the finishing items for our houses, and to do all the bathroom prep work (drains, waterproofing, and wall and floor treatments.) He also has plans for the foundations, too.

The bathroom needs a number of coats and drying time between courses, so Wille's plan is to stay over during the week and do the woodworking while the bathroom is drying. So it looks like he'll be the first person to sleep over in our house! At least we have beds, a kitchen, and electricity for him.

By the end of that week, we really should be substantially done, save the water and bathroom tiling. Janne will work on the water infrastructure over the next few months, and I plan to tile the bathroom when we're there in April.

No comments: